Marriott Marquis

Project focus: Whisper Walls Fabric Panels

Scope of Work:

One of the areas of work on this project that made it interesting was the Grand Ballroom. We had to install a 2” pre-manufactured fabric panel within a 2” metal grid system. What made this challenging was the coordination with the metal fabricators 10 weeks prior to the installation. This meant we had to acquire exact dimensions so all the materials could be ordered properly, and still meet the lead times allowing us to finish on schedule. It was very important that we had the knowledge and experience in our organization; they knew they had to get the sequencing right up front or it could have caused a tremendous issue of the grand ballroom not being able to open as scheduled.

Industry: Hotels